Starting in early August, you will see the following activities as we begin repairing the cable:
- Constructing two “freeze pits”, one in front of the Garneau Substation located at 11123 85 Avenue and one at 110 Street and 90 Avenue.
- Excavating along the bike lane on 110 Street north of 87 Avenue.
- Removing the section of damaged cables and replacing it with a new cable.
- Restoring the roadway and work areas.
Construction will begin in early August and is expected to be completed within two months, weather permitting. The typical hours of construction will be 7:00 a.m. – 9:00 p.m., Monday to Saturday, however, crews will be onsite 24/7 during this time to monitor the freeze pits.